Requirement Details
Electron Ion Collider

G-ESR.17
Requirement details, history, relationships and interfaces associated with requirement G-ESR.17
CURRENT RECORD
ARCHIVE RECORDS
RELATIONSHIPS
INTERFACES
| Record Date: 02/09/2026 20:55 | |||
| Identifier: | G-ESR.17 | WBS: | 6.02.04.02 |
| Date Modified: | TBD: | FALSE | |
| Status Date: | Status: | Approved | |
| Description: | The ESR shall have provisions made to accommodate a control system which can operate the ESR consistent will the overall control of the EIC and other EIC systems and to ensure the ESR meets all the Physics requirements needed to deliver the physics goals of the EIC. | ||
| Comments: | |||
| Record Date: 05/16/2025 17:04 | |||
| Identifier: | G-ESR.17 | WBS: | 6.07.02 |
| Date Modified: | TBD: | FALSE | |
| Status Date: | Status: | Approved | |
| Description: | The ESR shall have provisions made to accommodate a control system which can operate the ESR consistent will the overall control of the EIC and other EIC systems and to ensure the ESR meets all the Physics requirements needed to deliver the physics goals of the EIC. | ||
| Comments: | |||
| Record Date: 05/15/2025 20:34 | |||
| Identifier: | G-ESR.17 | WBS: | |
| Date Modified: | TBD: | FALSE | |
| Status Date: | Status: | ||
| Description: | The ESR shall have provisions made to accommodate a control system which can operate the ESR consistent will the overall control of the EIC and other EIC systems and to ensure the ESR meets all the Physics requirements needed to deliver the physics goals of the EIC. | ||
| Comments: | |||
| Record Date: 03/18/2025 18:05 | |||
| Identifier: | G-ESR.17 | WBS: | 6.07.02 |
| Date Modified: | TBD: | FALSE | |
| Status Date: | Status: | Approved | |
| Description: | The ESR shall have provisions made to accommodate a control system which can operate the ESR consistent will the overall control of the EIC and other EIC systems and to ensure the ESR meets all the Physics requirements needed to deliver the physics goals of the EIC. | ||
| Comments: | |||
| Record Date: 03/03/2025 18:11 | |||
| Identifier: | G-ESR.17 | WBS: | 6.09 |
| Date Modified: | TBD: | FALSE | |
| Status Date: | Status: | Approved | |
| Description: | The ESR shall have provisions made to accommodate a cryogenic system to cool and operate all elements which need cryogenic cooling . | ||
| Comments: | |||
| Record Date: 02/24/2025 18:26 | |||
| Identifier: | G-ESR.17 | WBS: | 6.08 |
| Date Modified: | TBD: | FALSE | |
| Status Date: | Status: | Approved | |
| Description: | The ESR shall have provisions made to accommodate a RF system capable of operating at parameters defined in MPT. [Document#:EIC-SEG-RSI-005] | ||
| Comments: | |||
| Record Date: 01/27/2025 16:43 | |||
| Identifier: | G-ESR.17 | WBS: | 6.08 |
| Date Modified: | TBD: | FALSE | |
| Status Date: | Status: | In Process | |
| Description: | The ESR shall utilize an RF system capable of operating at parameters defined in MPT. [Document#:EIC-SEG-RSI-005] | ||
| Comments: | |||
| Parents | |
| No parents. | |
| Children | |
| F-ESR-RF.06.02 | The ESR RF Systems within the tunnel shall operate within its yearly radiation exposure budget. |
| F-ESR-CONT.03 | The control system shall facilitate all machine protection systems required |
| F-ESR-INST.01 | The ESR instrumentation system shall include dual-plane Beam Position Monitors (BPMs) adjacent to each vertically focusing quadrupole. Provisions shall be made in the vacuum chamber design to install additional dual-plane BPMs at the horizontally focusing quadrupoles, if needed. |
| F-ESR-INST.02 | The ESR BPMs shall have turn-by-turn orbit measurement capability based on a single, remotely selectable bunch out of the fully filled bunch train to enable injection optimization. |
| F-ESR-INST.03 | The ESR instrumentation system shall include a beam current monitor to measure average beam current. |
| F-ESR-INST.04 | The ESR instrumentation system shall include a system to measure individual bunch charges and bunch pattern. |
| F-ESR-INST.05 | The ESR instrumentation system shall include a system to measure transverse beam profiles. |
| F-ESR-INST.06 | The ESR instrumentation system shall include a system to measure longitudinal beam profiles. |
| F-ESR-INST.07 | The ESR longitudinal bunch profile monitor needs turn-by-turn capability based on a single bunch in the fully filled bunch train to allow timing and energy adjustment for injection optimization. |
| F-ESR-INST.08 | The ESR instrumentation system shall include system to measure H & V betatron tunes. |
| F-ESR-INST.09 | The ESR instrumentation system shall facilitate all required feedback systems (slow transverse, longitudinal and transverse bunch-by-bunch) |
| F-ESR-INST.10 | The ESR instrumentation system shall include beam loss monitor system with detectors located only at select regions of the ESR. |
| F-ESR-RF.06.05 | The ESR RF System shall be designed to minimize unscheduled downtime, maintenance time and repair time to achieve ESR operational availability. |
This function not yet implemented.