G-EIS.2 | The EIS shall provide an electron beam having sufficient energy to meet the ESR beam requirements as set forth in the MPT. [Document#:EIC-SEG-RSI-005] |
G-EIS.3 | The EIS shall provide an electron beam with the RMS bunch momentum spread at extraction which meet the ESR beam requirements as set forth in the MPT. [Document#:EIC-SEG-RSI-005] |
G-EIS.4 | The EIS pre-injector shall provide an electron beam to the ESR having a horizontal beam emittance which is compatible with operation of the ESR. |
G-EIS.5 | The EIS pre-injector shall provide an electron beam to the ESR having a vertical beam emittance which is compatible with operation of the ESR. |
G-EIS.6 | The EIS shall inject into the ESR at a rate of 1[Hz]. |
G-EIS.7 | The EIS shall inject one bunch into the ESR whilst being able to provide 1 bunch per injection cycle. |
G-EIS.8 | The EIS shall provide an electron beam to the ESR having RMS Bunch lengths at extraction to meet beam requirements as set forth in the MPT. [Document#:EIC-SEG-RSI-005] |
G-EIS.9 | The EIS shall provide an electron beam to the ESR having the bunch charge at extraction to meet the beam requirements as set forth in the MPT. [Document#:EIC-SEG-RSI-005] |
G-EIS.10 | The EIS bunch replacement process shall deliver polarized replacement bunches capable of creating all the ESR polarization patterns needed to meet the physics goals. |
Children |
P-EIS-METL-INST-BPM.01 | For a bunch charge range of 100 pc to 10 nC, the BPM measurement resolution shall better than 100 um |
P-EIS-METL-INST-BPM.02 | The BPM acquisition rate shall be up to 100 Hz |
P-EIS-METL-INST-BPM.03 | The number of BPMs in the Linac-to-RCS transport line shall be TBD ea |
P-EIS-METL-INST-BPM.04 | The location of the BPMs shall be TBD |
P-EIS-METL-INST-BPM.05 | The BPM pick-up alignment accuracy with respect to to its nearby quadrapole magnet shall be better than 100 µm |
P-EIS-METL-INST-BPM.06 | The BPM button style pick-ups shall be rotated 45 degree configuration to avoid the synch light near the dipole bends. |
P-EIS-METL-INST-BPM.07 | The BPMs shall be used as input for beam trajectory correction and/or feedback to optimize transmission efficiency. |
P-EIS-METL-INST-BPM.08 | The BPMs shall be used to measure the beam energy and characterize the accelerator lattice. |
P-EIS-METL-INST-BPM.09 | The beam energy measurement resolution shall be 0.4 MeV |
P-EIS-METL-INST-CM.01 | An ICT and FCT shall be installed near the end of the transfer line. |
P-EIS-METL-INST-CM.02 | The bunch charge shall be measured with an accuracy better than <1 % |
P-EIS-METL-INST-CM.03 | The bunch charge shall be measured with the resolution of 10 pC |
P-EIS-METL-INST-CM.04 | The bunch charge monitor shall be used to measure transport efficiency. |
P-EIS-METL-INST-CM.05 | The FCT shall provide measurements of the bunch patterns being transported to the RCS. |
P-EIS-METL-INST-CM.06 | The number of ICTs in transfer line shall be 3 ea |
P-EIS-METL-INST-CM.07 | The number of FCTs in transfer line shall be TBD ea |
P-EIS-METL-INST-PM.01 | The transfer line shall include plunging YAG/OTR screens to measure beam position, transverse profiles and beam emittance measurements. |
P-EIS-METL-INST-PM.02 | The optical resolution for beam profile measurements shall be 50 um |
P-EIS-METL-INST-PM.03 | A YAG/OTR station at a dispersive location shall be used to determine the beam energy spread. |
P-EIS-METL-INST-PM.04 | The measurement capability shall be appropriate to measure a beam energy spread of 1 MeV |
P-EIS-METL-INST-PM.06 | The total number of profile monitors shall be TBD ea |
P-EIS-METL-INST-PM.05 | The measurement capability shall be appropriate to measure a beam emittance (Ref MPT Table 4.4.2.) for H & V of 35 um |
P-EIS-METL-INST-PM.07 | The locations of the profile monitors shall be TBD |