Record Date: 10/10/2024 00:00 | |||
Identifier: | G-DET-INF.4 | WBS: | 6.10.10 |
Date Modified: | TBD: | FALSE | |
Status Date: | Status: | APPROVED | |
Description: | Infrastructure systems for the collider hall shall include all power, water, environmental cooling, cryogenics, gas handling, clean compressed air delivery, space, fire protection, Helium Leak Detection, ODH Detection and any other Personnel Safety Systems, Cryo Protection, material handling and support systems required to operate the entire detector systems. | ||
Comments: |
No archive versions
Parents | |
No parents. | |
Children | |
F-DET-INF-COOL.1 | The WAH requires cooling capacity adequate for the heat generated by the detector, detector sub systems, detector support electronics and facility systems in the WAH. Comment: New airhandlers and cooling systems needed |
F-DET-INF-CRYO.1 | A cryogenic transfer system shall be provided within the collider hall to allow cryogenic distribution for the experimental solenoid. |
F-DET-INF-ELEC.1 | All detectors require isolated power and grounding from facilities power systems. This will be accomplished from existing and newly installed Delta/Wye transformers with a single point star grounding (AKA clean or magnet ground) scheme at the WAH. |
F-DET-INF-GAS.1 | Gas based detectors will require the appropriate gas mixing and handling systems. |
F-DET-INF-MECH.1 | Floors in the assembly and collider hall must be adequate to support the static and moving load of the experimental detector systems. Load limits need to be determined and verified. |