G-DET-INF.3
Requirement details, history, relationships and interfaces associated with requirement G-DET-INF.3
CURRENT RECORD
ARCHIVE RECORDS
RELATIONSHIPS
INTERFACES
Record Date: 07/14/2023 00:00 | |||
Identifier: | G-DET-INF.3 | WBS: | 6.10.10 |
Date Modified: | 07/14/2023 00:00 | TBD: | FALSE |
Status Date: | 07/14/2023 00:00 | Status: | APPROVED |
Description: | Infrastructure systems for the collider hall shall include all power, water, environmental cooling, cryogenics, gas handling, space, material handling and support systems required to operate the entire detector systems. | ||
Comments: |
No archive versions
Parents | |
No parents. | |
Children | |
F-DET-INF-COOL.1 | The WAH requires cooling capacity adequate for the heat generated by the detector, detector sub systems, detector support electronics and facility systems in the WAH. |
F-DET-INF-CRYO.1 | A cryogenic transfer system shall be provided within the collider hall to allow cryogenic distribution for the experimental solenoid. |
F-DET-INF-ELEC.1 | All detectors require isolated power and grounding from facilities power systems. This will be accomplished from existing and newly installed Delta/Wye transformers with a single point star grounding (AKA clean or magnet ground) scheme at the WAH. |
F-DET-INF-GAS.1 | Gas based detectors will require the appropriate gas handling systems. |
F-DET-INF-MECH.1 | Floors in the assembly and collider hall must be adequate to support the static and moving load of the experimental detector systems. |