Requirement Details
Electron Ion Collider
F-DET-INF.6
Requirement details, history, relationships and interfaces associated with requirement F-DET-INF.6
- CURRENT RECORD
- ARCHIVE RECORDS
- RELATIONSHIPS
- INTERFACES
Record Date: 10/10/2024 00:00 | |||
Identifier: | F-DET-INF.6 | WBS: | 6.10.10 |
Date Modified: | TBD: | FALSE | |
Status Date: | Status: | APPROVED | |
Description: | A structural support infrastructure must be provided that supports the weight of the infrastructure systems and peripheral equipment, and safely distributes that load to the ground. | ||
Comments: |
No archive versions
Parents | |
G-DET-INF.9 | The infrastructure systems will be functionally integrated with the other detectors, with the interaction region components, and with the facility infrastructure. |
G-DET-INF.10 | The infrastructure systems must fit within the available space in the experimental hall, and be consistent with the available infrastructure and resources. |
Children | |
P-DET-INF-CRYO.2 | The cryogenic transfer system will have a support structure and connectors that allow the central detector to be relocated between the experimental hall and the assembly area without disconnection. |
P-DET-INF-STD-RCS.2 | The RCS beampipe shall be supported by either the South Platform or the Central Barrel. |
P-DET-INF-STD-RCS.3 | If extra steel is needed for the fringe field, then support for it shall also be provided by either the South Platform or Central Barrel. |
P-DET-INF-STD-WEIGHT.1 | The weight limit of 1200 metric tons of the floor shall not be exceeded. |
P-DET-INF-STD-WEIGHT.2 | The combined weight of the Central Barrel shall not exceed 1200 metric tons. |
P-DET-INF-STD-WEIGHT.3 | The combined weight of both halves of the Hadron endcap shall not exceed 450 metric tons. |
P-DET-INF-STD-WEIGHT.4 | The combined weight of both halves of the Hadron endcap shall not exceed 275 metric tons. |
This function not yet implemented.