Requirement Details
Electron Ion Collider

F-DET-INF.4
Requirement details, history, relationships and interfaces associated with requirement F-DET-INF.4
CURRENT RECORD
ARCHIVE RECORDS
RELATIONSHIPS
INTERFACES
| Record Date: 05/16/2025 17:04 | |||
| Identifier: | F-DET-INF.4 | WBS: | 6.10.10 |
| Date Modified: | TBD: | FALSE | |
| Status Date: | Status: | Approved | |
| Description: | The configuration of the infrastructure systems within the detector will be coordinated to ensure efficient operation and to minimize adverse interactions between sub-systems. | ||
| Comments: | |||
| Record Date: 05/15/2025 20:34 | |||
| Identifier: | F-DET-INF.4 | WBS: | |
| Date Modified: | TBD: | FALSE | |
| Status Date: | Status: | ||
| Description: | The configuration of the infrastructure systems within the detector will be coordinated to ensure efficient operation and to minimize adverse interactions between sub-systems. | ||
| Comments: | |||
| Record Date: 01/27/2025 16:43 | |||
| Identifier: | F-DET-INF.4 | WBS: | 6.10.10 |
| Date Modified: | TBD: | FALSE | |
| Status Date: | Status: | Approved | |
| Description: | The configuration of the infrastructure systems within the detector will be coordinated to ensure efficient operation and to minimize adverse interactions between sub-systems. | ||
| Comments: | |||
| Parents | |
| G-DET-INF.9 | The infrastructure systems will be functionally integrated with the other detectors, with the interaction region components, and with the facility infrastructure. |
| G-DET-INF.10 | The infrastructure systems must fit within the available space in the experimental hall, and be consistent with the available infrastructure and resources. |
| Children | |
| P-DET-INF-STD-SVCGAP.1 | Area needed around pfRICH: 2000 cm2 + 10% = 2200 cm2 |
| P-DET-INF-STD-SVCGAP.2 | Area needed around EEEMcal: 2150cm2 + 10% = 2365 cm2 |
| P-DET-INF-STD-SVCGAP.3 | Area needed between CF tube and dRICH: 4350 cm2 + 10% = 4785 cm2 |
| P-DET-INF-STD-SVCGAP.4 | Area needed between dRICH boxes: 4800 cm2 + 10% = 5280 cm2 |
| P-DET-INF-STD-SVCGAP.5 | Area needed between dRICH and HCAL: 5650 cm2 + 10% = 6215 cm2 |
| P-DET-INF-STD-SVCGAP.7 | The positional tolerance of the cradle shall be within ±2mm in all directions. |
| P-DET-INF-STD-SVCGAP.8 | The adjustability of the cradle shall be at least ±25mm in the in the X,Z directions, and ±10mm in the Y direction. |
| P-DET-INF-STD-SVCGAP.9 | The positional tolerance of the of the Global Support Tube shall be within ±3mm in all directions. |
| P-DET-INF-STD-SVCGAP.10 | The adjustability of the Global Support Tube shall be at least ±10mm in all directions. |
| P-DET-INF-STD-SVCGAP.11 | The positional tolerance of the Pixel Support Tube shall be within ±1mm in all directions. |
| P-DET-INF-STD-SVCGAP.12 | The adjustability of the Pixel Support Tube shall be at least ±3mm in the X,Y directions, and ±5mm in the Z direction. |
| P-DET-INF-STD-SVCGAP.13 | The positional tolerance of the beampipe shall be within ±1mm in the X,Y directions, and ±5mm in the Z direction. |
| P-DET-INF-STD-SVCGAP.15 | The adjustability of the bellows shall be at least ±5mm in the Z direction. |
| P-DET-INF-STD-SVCGAP.14 | The rotational tolerance of the beampipe shall be within ±1mm mrad in the X, Y directions. |
| P-DET-INF-STD-SVCGAP.16 | The rotational adjustability of the flanges shall be at least ±1 degree in the X, Y directions. |
| P-DET-INF-STD-WEIGHT.6 | Subassembly weight should not exceed 90% of the assembly hall's 40 ton crane capacity to not be a critical lift. |
| P-DET-INF-STD-WEIGHT.7 | Subassembly weight should not exceed 90% of the experimental hall's 20 ton crane capacity to not be a critical lift. |
This function not yet implemented.